Implementing Benchmark Simulation Model No. 2 #934
Labels
costing
enhancement
New feature or request
iedo
master issue
model dev team
Issues directly related to the model development team
Priority:High
High Priority Issue or PR
property_model
Description
Our goal is to create a flowsheet for the Benchmark Simulation Model No. 2 (BSM2) which is a standard used in the wastewater treatment industry. BSM2 represents a full wastewater treatment plant (WWTP) that includes the activated sludge process as well as an anaerobic digestor, along with other units.
The ultimate goal is to utilize this detailed, plant-scale model, and prioritized BSM2-related model enhancements that would be required, to facilitate detailed technology comparisons via cost optimization for innovations proposed by teams under the IEDO 2336 effort.
Motivation
This will provide a detailed baseline for wastewater treatment processes and could be used for cost optimization studies.
Running TO-DO:
Questions , points of discussion, and minor issues
Z_h2s
!= 0?Tasks completed by June 2024 release:
Tasks completed by Mar 2024 release:
Tasks completed by Dec 2023 release:
Tasks completed by Sept 2023 release:
Tasks completed by the June 2023 release:
s_ic_rxns
for loop inadm1_reactions
? - no longer relevant/deletep_sat
name in ADM1 Properties Vapor topressure_sat
#941 Addressed in PR Minor Refinements to ADM1 #997The text was updated successfully, but these errors were encountered: